Information about the project

Project status

Current project

Category

Energy and industrial engineering

Title object

Khmelnytsk bio power plant

Shape attend

General contractor

Customer

KHMELNYTSK BIO POWER PLANT LIMITED LIABILITY COMPANY

Terms of works

April 2017 - December 2019

Design of biofuel power plant 46 MW

The design provides development of documentation Basic design stage and passing state expert review for straw-fired power plant including the following: 

  • Steam boiler– 130 MW;
  • Condensing turbine with generator – 46 MW;
  • Recycling water supply and chemically demineralized water system;
  • Transforming substation;
  • Straw barn with fuel conveying system;
  • Fuel gas cleaning system;
  • Ash removal system; 
  • Industrial and domestic waste treatment system;
  • Fire-fighting system;
  • Station-wide automatic control system;
  • Laboratory and administrative buildings etc.

 Overall area of the power plant – 16, 2 ha, building estate – 5,0 ha.