Information about the project

Project status

Current project

Category

Energy and industrial engineering

Title object

SE “Rivne NPP”

Shape attend

General contractor

Customer

SE “Rivne NPP”, State Enterprise “National Nuclear Energy Generating Company “Energoatom”

Terms of works

February 2020 - January 2021

Technical reequipping and introduction of system for forced “unfiltered” pressure release from active gas purification at power unit NO.4 OF Rivne NPP

The project provides technical reequipping and introduction of system for forced “unfiltered” pressure release from active gas purification at Power Unit No.4 of Rivne NPP.
 
Scope of construction works:
  • dismantling with subsequent installation of all assemblies of the system;
  • manufacture, installation of steel structures and pipelines;
  • welding quality control by non-destructive methods;
  • application of corrosion-resistant coating and thermal insulation;
  • integrated testing;
Introduction of efficient decompression system from active gas purification will exclude breakage of leak-tight enclosure as a result of pressure exceeding above its bearing capacity and uncontrolled discharge of radioactive mixture into environment that will enhance reliability of the power unit operation.