General overhaul of ammonia production units at the OAO NAK AZOT, Novomoskovsk, Russia

06.10.2010

A Contract has been signed for general overhauling of Ammonia-3 shop equipment at the OAO NAK AZOT. The project provides for the modernization of carbamide-3 shop with the transition to production of Russia's first granulated carbamide and the output expansion of up to 2 000 tons per day.

Scope of work:

The most important feature in the realization of this project is the accomplishment of 30- 40 percent reduction of discharges into water bodies, emissions of ammonia and hazardous dust pollutants into the atmosphere.