Modernization of boiler ТПП-312А on Power Units No. 1, 4 of Zaporozhskaya TPP

06.01.2010 Work implementation on repair of dust preparation system of boiler unit ТПП-312А on Power Units No. 1,4 of Zaporozhskaya Thermal Power Plant is completed. At the same time preparation and deaerator diagnostics of turbine house of power unit No.4 was implemented. Boiler modernization will allow improving fuel efficiency and will increase technical-economic indicator of power unit in the whole.