Piles tests under the project “NSC Design, Construction and Commissioning” for “Shelter” Object at Chernobyl NPP

04.09.2009 The activities on piles tests under the project NSC Design, Construction and Commissioning for Shelter Object at Chernobyl NPP have been finalized.
The project included fabrication, driving and complex of tests of special steel piles with length 27m. Steel piles are planned to be used for arrangement of a part of foundations for New Safety Confinement (Shelter) which is constructed above the destroyed Unit No.4 at Chernobyl NPP.