Technical reequipping of power unit No.1 SE Khmelnytskyi NPP

25.03.2019

Company successfully completed works for reconstruction of first of three water supply systems of essential consumers of power unit No.1 SE Khmelnytskyi NPP.
Specialists of the company executed:
  • dismantling of pumping units type D-4000-95;
  • installation of new pumping units type ATSNA 4000-95/8-2а;
  • installation of electrical equipment, instrumentation, cable and wire products of new pumping units;
  • startup and adjustment works;
Works were executed in a high quality manner, as per design documentation and approved repair schedule of the power unit. Following the results of individual test of assembled units, permit was obtained for commissioning of the equipment.

Replacement of outdated pumping units with new of more reliable design with steel enclosure, that meet requirements of PN AE G-7-008-89, will enable to extend service life of the power unit above designed period (more than 30 years).