Technical reequipping of power unit No.1 SE Khmelnytskyi NPP

18.02.2019

Company signed contract for works on technical reequipping and introduction of system for forced “unfiltered” pressure release from leak-tight enclosure system at power unit No.1 Khmelnytskyi NPP.
Project provides complete package of works, including:
  • dismantling with subsequent installation of all assembly components of the system and steel structures;
  • weld quality monitoring by non-destructive methods and integrated tests;
  • applying corrosion-resistant protection and heat insulation.
Introduction of efficient forced pressure release system from leak-tight enclosure system will allow to enhance reliability of the power unit operation.

Customer: SE Khmelnytskyi NPP, State Enterprise “National Nuclear Energy Generating Company “Energoatom”.