Construction of redundant electric boiler house for heat supply of New Safe Confinement (NSC) at SSE “Chornobyl NPP”

Object name:

New Safe Confinement at SSE CNPP

Form of participation:

General Contract

Customer:

SSE «Chornobyl NPP»

Project execution period     
(commencement – scheduled completion):

April 2017 - June 2018

The project provides:

  • development of design documentation for construction of object (working design);
  • passing expert review of construction project with obtaining expert report regarding review of design documents (positive);
  • execution of construction and installation works including:
  • installation of 4 boilers total capacity 5 MW;
  • construction of boiler house and transformer substation buildings,
  • external and internal installation and electrical works,
  • laying external networks of cable lines,
  • laying external heat supply pipelines of drinking water,
  • startup and adjustment works;
  • execution of field supervision over construction of the object;
  • support of the Customer during commissioning of the object.

 


Возврат к списку

Our current projects

Construction of redundant electric boiler house for heat supply of New Safe Confinement (NSC) at SSE “Chornobyl NPP”

Design of biofuel power plant 46 MW

Construction of on-site spent nuclear fuel dry storage facility (ISF-2)

Conducting experimental-adjustment works using full-scale large simulators of main process equipment of Central Spent Fuel Storage Facility (CSFSF)

Pivdenteploenergomontazh, AT
vul. Pushkinska, 27, Kiev
01601, Ukraine
tel: +38 (044) 499-65-55; 499-65-33
fax: +38 (044) 499-65-57
marketing@utem.kiev.ua