Implementation of advanced cost-effective solutions ua en
 


Current Projects


Reconstruction of 2nd stage of biofuel power plant 18MW in urban-type settlement Ivankiv, Kyiv oblast.

Object:

ECOTPP "Ivankiv"

Form of participation:

Prime contract

Customer:

Biogasenergo LLC

Project life (start - planned finish):

August 2017 – March 2018


The project provides:
∙ Correction of detailed design documentation;
∙ Additional delivery of main process equipment;
∙ Completion of construction and installation works of 2nd stage;
∙ Designing and introduction of APCS of the plant.

The power plant will operate with maximum automation level of all processes for this technology, while flue gas cleaning system will assure emissions level which meets European standards.

Возврат к списку

Our current projects

Construction of redundant electric boiler house for heat supply of New Safe Confinement (NSC) at SSE “Chornobyl NPP”

Design of biofuel power plant 46 MW

Construction of on-site spent nuclear fuel dry storage facility (ISF-2)

Conducting experimental-adjustment works using full-scale large simulators of main process equipment of Central Spent Fuel Storage Facility (CSFSF)

Pivdenteploenergomontazh, AT
vul. Pushkinska, 27, Kiev
01601, Ukraine
tel: +38 (044) 499-65-55; 499-65-33
fax: +38 (044) 499-65-57
marketing@utem.kiev.ua